Summer Projects on Campus this Year

Posted on June 08, 2019 in: General News

Summer Projects on Campus this Year

- Gilbertson Stained Glass will be working on the remaining stained glass windows around the church (scraping, sanding, repair glazing, replacing rotted wood, priming and painting. They have already started and will take 4 to 6 weeks, depending upon weather.

 - Cramer Construction will be working on the doors for the Chapel and Heim Hall. Wood is on order.

- Krause Konstruction will start working on replacing the mis-colored mortar and painting the exterior of the upper part of the church starting after the grade school is out - could also take 4 to 6 weeks.

- Lange Custom Woodworking will start working on the church doors (3 sets on McHenry Street, to be completed in 3 phases).

 